NIT South Renovations - Backlands Reconstruction

Project Description | Schedule | Project Team | Back to Archive

Archived: March 1, 2011

Project Description

This project entails the complete renovation of the south container yard of Norfolk International Terminals. The entire project area comprises approximately 150 acres and is being completed in stages so as not to interfere with cargo operations. Work includes utility upgrades and pavement improvements.

Original Estimated Construction Cost (Areas 3 and 4): $27,535,000
Change Order for Work in Areas 5 Through 7: $14,900,000
Change Order for Work in Area 8: $10,000,000

Change Order for Work in Areas 10A Through 12B: $4,900,000
Change Order for Work in Area 9: $6,900,000

Back to Top

Schedule

Phase
Target
Actual
Start Design January 2005 January 2005
Finish Design August 2005 August 2005
RFQ Issued July 2005 July 17, 2005
RFQ Responses Due August 2005 August 5, 2005
Bids Due September 2005 September 20, 2005
Notice to Proceed October 2005 November 14, 2005

Substantial Completion Area 3

September 2006 June 2, 2006
Substantial Completion Area 4 November 2007 December 2006
Substantial Completion Area 5/6 November 2007 September 2007
Substantial Completion Area 6/7 November 2008 November 2008
Substantial Completion Area 8 July 2009 October 31, 2009
Substantial Completion Area 9 December 2012 August 2010
Final Completion December 2012 August 2010

Back to Top

Project Team

Project Manager Kevin P. Abt, PE Tel: 757-683-2139
  Virginia Port Authority Fax: 757-683-2151
     
Design Engineer Moffatt & Nichol Tel: 757-628-8222
  800 World Trade Center Fax: 757-628-8244
  Norfolk, VA 23510  
     
Contractor Branscome, Inc. Tel: 757-229-2504
  4551 John Tyler Hwy Fax: 757-220-0390
  Williamsburg, VA 23185  

Back to Top

 

 

Click to Enlarge Image
NIT South Backlands circa 2002

Click to Enlarge Image
Completed NIT South Backlands October 2010


 