Fender Maintenance
Project Description | Schedule | Project Team | Back to Archive
Archived: April 29, 2005
Project Description
The project involves the on-call demolition, removal, disposal and/or repair of fenders. Work may be required at any one, or all, of the three marine terminals owned by the Virginia Port Authority. The contract term will be one (1) year, with the option to renew on a yearly basis not to exceed an aggregate total of five (5) years. Unit prices for the renewal terms will be negotiated at the time of renewal.
Estimated Construction Cost: N/A
Back to Top
Schedule
Phase |
Target |
Actual |
| Start Design |
July 2002 |
July 2002 |
| Finish Design |
September 2003 |
September 2003 |
| Advertise |
October 19, 2003 |
October 19, 2003 |
| Bids Due |
November 11, 2003 |
November 11, 2003 |
| Notice to Proceed |
January 2004 |
February 2, 2004 |
| Substantial Completion |
N/A |
N/A |
| Final Completion |
N/A |
N/A |
Back to Top
Project Team
| Project Manager |
Heath K. Pope, P.E. |
Tel: 757-628-8222 |
| |
Moffatt & Nichol |
Fax: 757-628-8244 |
| |
|
|
| Contractor |
Marine Contracting |
Tel: 757-460-4666 |
| |
P.O. Box 5525 |
Fax: 757-363-9647 |
| |
Virginia Beach, VA 23471 |
|
Back to Top |
|

Fender Work at PMT 3/16/05

Performing Fender Repairs

Newly Installed Fenders at PMT
|
 |