The project involves the on-call demolition, removal, disposal and/or repair of fenders. Work may be required at any one, or all, of the three marine terminals owned by the Virginia Port Authority. The contract term will be one (1) year, with the option to renew on a yearly basis not to exceed an aggregate total of five (5) years. Unit prices for the renewal terms will be negotiated at the time of renewal.

Estimated Construction Cost: N/A

Back to Top

Schedule

Phase
Target
Actual
Start Design July 2002 July 2002
Finish Design September 2003 September 2003
Advertise October 19, 2003 October 19, 2003
Bids Due November 11, 2003 November 11, 2003
Notice to Proceed January 2004 February 2, 2004
Substantial Completion N/A N/A
Final Completion N/A N/A

Back to Top

Project Team

Project Manager Heath K. Pope, P.E. Tel: 757-628-8222
  Moffatt & Nichol Fax: 757-628-8244
     
Contractor Marine Contracting Tel: 757-460-4666
  P.O. Box 5525 Fax: 757-363-9647
  Virginia Beach, VA 23471  

Back to Top

 

 


Click to Enlarge Image
Fender Work at PMT 3/16/05

Click to Enlarge Image
Performing Fender Repairs

Click to Enlarge Image
Newly Installed Fenders at PMT

 


 

About This Site
Moffatt & Nichol Web Site