Project Description
This project involves the work necessary to make the following modifications to three (3) Kone Cranes at Portsmouth Marine Terminal: Complete the removal of the shore hoist systems, install diesel enclosures and diesel generator systems (diesel generator systems provided by owner), and raise cranes approximately 9 feet. There are also several options, including painting, replacing the PLC system and control systems, and adding new crane management and diagnostic systems.
Estimated Construction Cost: $6,077,200 (Includes Painting)
Back to Top
Schedule
Phase |
Target |
Actual |
| Start Design |
February 2005 |
February 2005 |
| Finish Design |
February 2006 |
February 2006 |
| Advertise |
April 2006 |
April 2, 2006 |
| Bids Due |
April 28, 2006 |
May 11, 2006 |
| Notice to Proceed |
June 1, 2006 |
June 19, 2006 |
| Substantial Completion |
May 2007 |
September 2007 |
| Final Completion |
June 2007 |
December 2007 |
Back to Top
Project Team
| Project Manager |
James E. Poff , P.E. |
Tel: 757-628-8222 |
| |
Moffatt & Nichol |
Fax: 757-628-8244 |
| |
|
|
| Contractor |
East Coast Cranes |
Tel: 843-884-3929 |
| |
P.O. Box 328 |
Fax: 843-884-3929 |
| |
Isle of Palms, SC 29451 |
|
Back to Top
|
|

Completed Kone Cranes

New Diesel House

New Fuel Tank

Electrical Modifications
|
 |