Kone Crane Modifications

Project Description | Schedule | Project Team | Back to Archive

Archived: January 31, 2008

Project Description

This project involves the work necessary to make the following modifications to three (3) Kone Cranes at Portsmouth Marine Terminal: Complete the removal of the shore hoist systems, install diesel enclosures and diesel generator systems (diesel generator systems provided by owner), and raise cranes approximately 9 feet. There are also several options, including painting, replacing the PLC system and control systems, and adding new crane management and diagnostic systems.

Estimated Construction Cost: $6,077,200 (Includes Painting)

Back to Top

Schedule

Phase
Target
Actual
Start Design February 2005 February 2005
Finish Design February 2006 February 2006
Advertise April 2006 April 2, 2006
Bids Due April 28, 2006 May 11, 2006
Notice to Proceed June 1, 2006 June 19, 2006
Substantial Completion May 2007 September 2007
Final Completion June 2007 December 2007

Back to Top

Project Team

Project Manager James E. Poff , P.E. Tel: 757-628-8222
  Moffatt & Nichol Fax: 757-628-8244
     
Contractor East Coast Cranes Tel: 843-884-3929
  P.O. Box 328 Fax: 843-884-3929
  Isle of Palms, SC 29451  

Back to Top

 

 

 

 


Click to Enlarge Image
Completed Kone Cranes

Click to Enlarge Image
New Diesel House

Click to Enlarge Image
New Fuel Tank

Click to Enlarge Image
Electrical Modifications

 