Project Description

The project calls for the installation of approximately 11,000 feet of track, ties and ballast, several switches, heavy-duty pavement in the rail yard area, site civil utility work and electrical work. When complete, this project will provide a centralized rail yard for NIT and significantly increase rail capacity at the terminal.

Estimated Construction Cost: $16,476,450

Back to Top

Schedule

Phase
Target
Actual
Start Design June 29, 2006 June 29, 2006
Finish Design February 2007 March 2007
Advertise April 2007 April 1, 2007
Bids Due May 8, 2007 May 8, 2007
Notice to Proceed August 1, 2007 August 1, 2007
Substantial Completion July 2, 2008 October 2008
Final Completion August 1, 2008 November 2008

Back to Top

Project Team

Project Manager Kevin P. Abt, P.E. Tel: 757-683-2139
  Virginia Port Authority Fax: 757-683-2151
     
Design Engineer TranSystems Tel: 757-627-1112
  Town Point Center Fax: 757-627-1113
  150 Boush Street, Suite 1000
 
  Norfolk, VA 23510  
     
Contractor H&B Railroad Company, Inc. Tel: 757-365-9512
 

903 A Main Street

Fax: 757-365-9515
  Smithfield, VA 23430  

Back to Top

 

 


Click to Enlarge Image
Project Location

Click to Enlarge Image
Aerial View of Completed Rail Yard

Click to Enlarge Image
Completed Rail Yard

Click to Enlarge Image
Training Operations

 

About This Site
Moffatt & Nichol Web Site