NIT Central Rail Project
Project Description | Schedule | Project Team | Back to Archive
Archived: April 27, 2009
Project Description
The project calls for the installation of approximately 11,000 feet of track, ties and ballast, several switches, heavy-duty pavement in the rail yard area, site civil utility work and electrical work. When complete, this project will provide a centralized rail yard for NIT and significantly increase rail capacity at the terminal.
Estimated Construction Cost:
$16,476,450
Back to Top
Schedule
Phase |
Target |
Actual |
| Start Design |
June 29, 2006 |
June 29, 2006 |
| Finish Design |
February 2007 |
March 2007 |
| Advertise |
April 2007 |
April 1, 2007 |
| Bids Due |
May 8, 2007 |
May 8, 2007 |
| Notice to Proceed |
August 1, 2007 |
August 1, 2007 |
| Substantial Completion |
July 2, 2008 |
October 2008 |
| Final Completion |
August 1, 2008 |
November 2008 |
Back to Top
Project Team
| Project Manager |
Kevin P. Abt, P.E. |
Tel: 757-683-2139 |
| |
Virginia Port Authority |
Fax: 757-683-2151 |
| |
|
|
| Design Engineer |
TranSystems |
Tel:
757-627-1112 |
| |
Town Point Center |
Fax:
757-627-1113 |
| |
150 Boush Street, Suite 1000
|
|
| |
Norfolk, VA 23510 |
|
| |
|
|
| Contractor |
H&B Railroad Company, Inc. |
Tel:
757-365-9512 |
| |
903 A Main Street |
Fax:
757-365-9515 |
| |
Smithfield, VA 23430 |
|
Back to Top |
|

Project Location

Aerial View of Completed Rail Yard

Completed Rail Yard

Training Operations
|
 |