Project Description

This project comprises an area of approximately 19 acres to the north of the existing NIT North pavement and includes clearing, pavement and site demolition, single-story building demolition, E&S control, earthwork, and placement of aggregate base, and all other miscellaneous items specified within the Construction Plans and Specifications.

Paving the site is included with the NIT South Backlands Stage II project as an alternate bid item.

Estimated Construction Cost: $1,328,089

Back to Top

Schedule

Phase
Target
Actual
Start Design February 2005 February 2005
Finish Design May 2005 May 2005
Advertise May 23, 2005 May 23, 2005
Bids Due June 23, 2005 June 30, 2005
Notice to Proceed August 18, 2005 August 2, 2005
Substantial Completion November 15, 2005 December 31, 2005
Final Completion December 15, 2005 January 31, 2006

Back to Top

Project Team

Project Manager Kevin P. Abt, P.E. Tel: 757-683-2139
  Virginia Port Authority Fax: 757-683-2151
     
Design Engineer Moffatt & Nichol Tel: 757-628-8222
  440 World Trade Center Fax: 757-628-8244
  Norfolk, VA 23510  
     
Contractor Branscome, Inc. Tel: 757-229-2504
  4551 John Tyler Hwy Fax: 757-220-0390
  Williamsburg, VA 23185  

Back to Top

 

 

 


Click to Enlarge Image
Grading Project Area

Click to Enlarge Image
Site Clearing and Demo

Click to Enlarge Image
Site Clearing and Demo


 

About This Site
Moffatt & Nichol Web Site