NIT North Expansion Grading
Project Description | Schedule | Project Team | Back to Archive
Archived: March 7, 2006
Project Description
This project comprises an area of approximately 19 acres to the north of the existing NIT North pavement and includes clearing, pavement and site demolition, single-story building demolition, E&S control, earthwork, and placement of aggregate base, and all other miscellaneous items specified within the Construction Plans and Specifications.
Paving the site is included with the NIT South Backlands Stage II project as an alternate bid item.
Estimated Construction Cost: $1,328,089
Back to Top
Schedule
Phase |
Target |
Actual |
| Start Design |
February 2005 |
February 2005 |
| Finish Design |
May 2005 |
May 2005 |
| Advertise |
May 23, 2005 |
May 23, 2005 |
| Bids Due |
June 23, 2005 |
June 30, 2005 |
| Notice to Proceed |
August 18, 2005 |
August 2, 2005 |
| Substantial Completion |
November 15, 2005 |
December 31, 2005 |
| Final Completion |
December 15, 2005 |
January 31, 2006 |
Back to Top
Project Team
| Project Manager |
Kevin P. Abt, P.E. |
Tel: 757-683-2139 |
| |
Virginia Port Authority |
Fax: 757-683-2151 |
| |
|
|
| Design Engineer |
Moffatt & Nichol |
Tel: 757-628-8222 |
| |
440 World Trade Center |
Fax: 757-628-8244 |
| |
Norfolk, VA 23510 |
|
| |
|
|
| Contractor |
Branscome, Inc. |
Tel: 757-229-2504 |
| |
4551 John Tyler Hwy |
Fax: 757-220-0390 |
| |
Williamsburg, VA 23185 |
|
Back to Top
|
|