NIT North Pavement Expansion

Project Description | Schedule | Project Team | Back to Archive

Archived: January 12, 2007

Project Description

This project comprises an area of approximately 19 acres to the north of the existing NIT North pavement and includes E&S control, fine grading, utility installation, RCC pavement and cast-in-place concrete pavement, and all other miscellaneous items specified within the Construction Plans and Specifications.

Estimated Construction Cost: $11,238,000

Back to Top

Schedule

Phase
Target
Actual
Start Design February 2005 February 2005
Finish Design August 2005 August 2005
Advertise October 2005 October 2005
Bids Due November 2005 November 2005
Notice to Proceed December 2005 January 12, 2006
Substantial Completion December 2006 December 2006
Final Completion January 2007 January 2007

Back to Top

Project Team

Project Manager Kevin P. Abt, P.E. Tel: 757-683-2139
  Virginia Port Authority Fax: 757-683-2151
  World Trade Center  
  Norfolk, VA 23510  
     
Design Engineer Moffatt & Nichol Tel: 757-628-8222
  440 World Trade Center Fax: 757-628-8244
  Norfolk, VA 23510  
     
Contractor Branscome, Inc. Tel: 757-229-2504
  4551 John Tyler Hwy Fax: 757-220-0390
  Williamsburg, VA 23185  

Back to Top

 

 

 


Click to Enlarge Image
Paving Project Area

Click to Enlarge Image
Completed Pavement January 2007

Click to Enlarge Image
Grading in Progress

Click to Enlarge Image
Completed Section of Transfer Zone Pavement

 