NIT North Pavement Expansion
Project Description | Schedule | Project Team | Back to Archive
Archived: January 12, 2007
Project Description
This project comprises an area of approximately 19 acres to the north of the existing NIT North pavement and includes E&S control, fine grading, utility installation, RCC pavement and cast-in-place concrete pavement, and all other miscellaneous items specified within the Construction Plans and Specifications.
Estimated Construction Cost: $11,238,000
Back to Top
Schedule
Phase |
Target |
Actual |
| Start Design |
February 2005 |
February 2005 |
| Finish Design |
August 2005 |
August 2005 |
| Advertise |
October 2005 |
October 2005 |
| Bids Due |
November 2005 |
November 2005 |
| Notice to Proceed |
December 2005 |
January 12, 2006 |
| Substantial Completion |
December 2006 |
December 2006 |
| Final Completion |
January 2007 |
January 2007 |
Back to Top
Project Team
| Project Manager |
Kevin P. Abt, P.E. |
Tel: 757-683-2139 |
| |
Virginia Port Authority |
Fax: 757-683-2151 |
| |
World Trade Center |
|
| |
Norfolk, VA 23510 |
|
| |
|
|
| Design Engineer |
Moffatt & Nichol |
Tel: 757-628-8222 |
| |
440 World Trade Center |
Fax: 757-628-8244 |
| |
Norfolk, VA 23510 |
|
| |
|
|
| Contractor |
Branscome, Inc. |
Tel: 757-229-2504 |
| |
4551 John Tyler Hwy |
Fax: 757-220-0390 |
| |
Williamsburg, VA 23185 |
|
Back to Top
|
|

Paving Project Area

Completed Pavement January 2007

Grading in Progress

Completed Section of Transfer Zone Pavement
|
 |