NIT North Pavement Replacement
Project Description | Schedule | Project Team | Back to Archive
Archived: March 14, 2005
Project Description
The project involves the demolition of approximately 40 acres of existing asphalt concrete paving, installation of a PVC drainage system and extension of the existing trench drain system, installation of new concrete pavement and asphalt concrete pavement, repairs to the asphalt concrete yard adjacent to the concrete and pavement markings.
Estimated Construction Cost: $15,000,000
Back to Top
Schedule
Phase |
Target |
Actual |
| Start Design |
April 2002 |
April 2002 |
| Finish Design |
September 2002 |
October 2002 |
| Advertise |
November 2002 |
November 2002 |
| Bids Due |
December 2003 |
January 2003 |
| Notice to Proceed |
N/A |
March 17, 2003 |
| Substantial Completion |
January 2005 |
January 2005 |
| Final Completion |
February 2005 |
March 2005 |
Back to Top
Project Team
| Project Manager |
Kevin P. Abt, P.E. |
Tel: 757-683-2139 |
| |
Virginia Port Authority |
Fax: 757-683-2151 |
| |
|
|
| Contractor |
Branscome, Inc. |
Tel: 757-622-4200 |
| |
3425 Westminster Ave. |
Fax: 757-533-5383 |
| |
Norfolk, VA 23504 |
|
| |
|
|
| |
|
|
Back to Top
|
|

Aerial View of Project Site 2/19/05

Aerial View Project Site 6/1/04

Placing RCC