NIT North Wharf Extension

Project Description | Schedule | Project Team | Back to Archive

Archived: October 1, 2008

Project Description

The project generally includes, but is not limited to: extension of the existing wharf approximately 900 feet north, dredging of the adjacent access channel and berth area, site civil work behind the wharf structure, and associated utility work. The project also includes the procurement of three container cranes similar to those at the south end of the NIT North Wharf.

Estimated Construction Cost: $34,000,000

Back to Top

Schedule

Phase
Target
Actual
Start Design March 1, 2006 March 1, 2006
Finish Design August 7, 2006 September 8, 2006
Advertise August 30, 2006 September 17, 2006
Bids Due September 30, 2006 October 17, 2006
Notice to Proceed October 16, 2006 January 3, 2007
Substantial Completion May 31, 2008 June 30, 2008
Final Completion June 30, 2008 July 30, 2008

Back to Top

Project Team

Project Manager Kevin P. Abt, P.E. Tel: 757-683-2139
  Virginia Port Authority Fax: 757-683-2151
     
Design Engineer Parsons Brinckerhoff Tel: 757-466-1732
  6161 Kempsville Circle, Ste. 110 Fax: 757-466-1493
  Norfolk, VA 23502  
     
Construction Contractor Tidewater-Skanska Tel: 757-420-4140
  809 S Military Hwy Fax: 757-420-3551
  Virginia Beach, VA 26464  
     
Dredging Contractor Norfolk Dredging Tel: (757) 547-9391
 

110 Centerville Turnpike North

Fax: (757) 547-2833
  Chesapeake, VA 23320  

Back to Top

 

 

 

Click to Enlarge Image
Location of NIT North Wharf Extension

Click to Enlarge Image
New North Wharf

Click to Enlarge Image
View of New Wharf from Pier 3

 

 