Project Description
The project is a complete reconstruction of 4,230 linear feet of the existing facility and will be completed in four (4) stages. The demolition work involves approximately 185,000 square feet of existing concrete wharf and the supporting concrete piles, 190,000 square feet of asphalt concrete paving and removal of underground utilities. Demolition also includes the removal and disposal of four existing 50-foot gage container cranes at the facility. The construction work involves the installation of pre-cast concrete piles, sheet piling, a cast-in-place concrete wharf structure, asphalt concrete pavement, installation/relocation of various utilities and assorted minor tasks.
Estimated Construction Cost: $84,000,000
Back to Top
Schedule
Phase |
Target |
Actual |
| Start Design |
|
|
| Finish Design |
May 2002 |
June 2002 |
| Advertise |
July 2002 |
July 2002 |
| Bids Due |
August 2002 |
August 2002 |
| Notice to Proceed |
September 2002 |
September 2002 |
| Substantial Completion Stage I |
August 2003 |
December 2003 |
| Final Completion Stage I |
September 2003 |
January 2004 |
| Substantial Completion Stage II |
July 2004 |
June 2004 |
| Final Completion Stage II |
August 2004 |
July 2004 |
| Substantial Completion Stage III |
December 2004 |
November 2004 |
| Final Completion Stage III |
January 2005 |
December 2004 |
| Substantial Completion Stage IV |
August 2005 |
May 2005 |
| Final Completion Stage IV |
September 2005 |
September 30, 2005 |
Back to Top
Project Team
Project Manager |
Kevin P. Abt, P.E. |
Tel: 757-683-2139 |
|
Virginia Port Authority |
Fax: 757-683-2151 |
| |
|
|
Design Engineer |
Moffatt & Nichol |
Tel: 757-628-8222 |
|
440 World Trade Center |
Fax: 757-628-8244 |
| |
Norfolk, VA 23510 |
|
|
|
|
Contractor |
Tidewater-Skanska |
Tel: 757-420-4140 |
|
809 S Military Hwy |
Fax: 757-420-3551 |
|
Virginia Beach, VA 26464 |
|
Back to Top
|
|