This project consists of the construction of a turning dolphin to replace the existing fender system on the northwest corner of Pier C, as well as the installation of a 60-ton bollard at Pier B. The Pier C turning dolphin will provide a pivot point for berthing ships in the strong current. Work on this project will include mobilization/demobilization, construction surveying, erosion and sediment control, site demolition, utility work, construction, site restoration and clean-up, removal and disposal of debris, and incidental work as needed.

Estimated Construction Cost: $1,180,778

Back to Top

Schedule

Phase
Target
Actual
Start Design December 15, 2003 December 15, 2003
Finish Design June 15, 2004 July 9, 2004
Advertise May 30, 2004 August 8, 2004
Bids Due June 1, 2004 September 7, 2004
Notice to Proceed July 15, 2004 October 14, 2004
Substantial Completion December 30, 2004 May 23, 2005
Final Completion January 30, 2005 June 1, 2005

Back to Top

Project Team

Project Manager Kevin P. Abt, P.E. Tel: 757-683-2139
  Virginia Port Authority Fax: 757-683-2151
     
Design Engineer Moffatt & Nichol Tel: 757-628-8222
  440 World Trade Center Fax: 757-628-8244
  Norfolk, VA 23510  
     
Contractor Marine Contracting Corporation Tel: 757-460-4666
  P.O. Box 5525 Fax: 757-363-9647
  Virginia Beach, VA 23471  