NNMT Pier C South Crane Tie-Downs
Project Description | Schedule | Project Team | Back to Archive
Archived: July 7, 2005
Project Description
The project involves the work necessary to install four (4) new crane tie--downs and two (2) new crane stowage sockets in the concrete wharf and relocate four (4) existing crane tie-downs and two (2) existing crane stowage sockets that are embedded in the Pier C concrete deck at Newport News Marine Terminal. Work will include all concrete demolition, cast-in-place concrete, reinforcing steel, structural steel and structural welding necessary to relocate the old and install the new tie-downs.
Estimated Construction Cost: $91,227
Back to Top
Schedule
Phase |
Target |
Actual |
| Start Design |
|
|
| Finish Design |
|
|
| Advertise |
January 2, 2005 |
January 2, 2005 |
| Bids Due |
January 18, 2005 |
January 18, 2005 |
| Notice to Proceed |
March 21, 2005 |
March 21, 2005 |
| Substantial Completion |
May 8, 2005 |
N/A |
| Final Completion |
June 7, 2005 |
July 7, 2005 |
Back to Top
Project Team
| Project Manager |
Heath K. Pope, P.E. |
Tel: 757-628-8222 |
| |
Moffatt & Nichol |
Fax: 757-628-8244 |
| |
|
|
| Contractor |
T.J. Crooks, Inc. |
Tel: 757-436-2897 |
| |
138 Tilden Avenue |
Fax: 757-436-6589 |
| |
Chesapeake, VA 23320 |
|