Project Description
Plum Point Park is a joint effort by the VPA and the City of Norfolk. It is a construction project that the VPA will fund to meet mitigation requirements for terminal renovations at NIT. The City will maintain it as a public park into perpetuity. The project involves clean-up of site debris, excavation and installation of Class II and Class III riprap for 1600 feet of shoreline, removal of approximately 500 deteriorated piles, planting of 1-acre of wetlands, paving of a bike trail, and incidental landscaping for a 5-acre public park.
Estimated Construction Cost: $1,600,000
Back to Top
Schedule
Phase |
Target |
Actual |
| Start Design |
Summer 2002 |
August 25, 2002 |
| Finish Design |
January 2003 |
June 15, 2003 |
| Advertise |
June 15, 2003 |
N/A |
| Bids Due |
July 3, 2003 |
July 8, 2003 |
| Notice to Proceed |
August 1, 2003 |
August 25, 2003 |
| Substantial Completion |
November 8, 2003 |
April 1, 2004 |
| Final Completion |
April 30, 2004 |
July 31, 2004 |
Back to Top
Project Team
| Project Manager |
Barbara Bodenstein, E.I.T. |
Tel: 757-628-8222 |
| |
Moffatt & Nichol |
Fax: 757-628-8244 |
| |
|
|
| Landscape Architect |
WPL, Inc. |
Tel: 757-431-1041 |
| |
242 Mustang Trail, Suite 8 |
Fax: 757-463-1412 |
| |
Virginia Beach, VA 23542 |
|
| |
|
|
| Contractor |
Coastal Design & Construction |
Tel: 804-693-4158 |
| |
6346 Allmondsvile Road |
Fax: 804-693-0064 |
| |
Gloucester, VA 23601 |
|
Back to Top
|
|