PMT Building 100 Roof Repairs
Project Description | Schedule | Project Team | Back to Archive
Archived: July 5, 2005
Project Description
This project consists of providing a new membrane recovery roof system over the existing roof while removing abandoned penetrations. Downspouts will also be repaired and replaced, and loose or damaged insulation will be repaired or resecured. Additional interior lighting will also be installed.
Estimated Construction Cost: $575,000
Back to Top
Schedule
Phase |
Target |
Actual |
| Start Design |
October 20, 2003 |
October 20, 2003 |
| Finish Design |
May 15, 2004 |
May 11, 2004 |
| Advertise |
May 30, 2004 |
May 30, 2004 |
| Bids Due |
June 30, 2004 |
July 2, 2004 |
| Notice to Proceed |
July 15, 2004 |
August 31, 2004 |
| Substantial Completion |
November 30, 2004 |
April 25, 2005 |
| Final Completion |
December 30, 2004 |
June 24, 2005 |
Back to Top
Project Team
| Project Manager |
Heath K. Pope, P.E. |
Tel: 757-628-8222 |
| |
Moffatt & Nichol |
Fax: 757-628-8244 |
| |
|
|
| Design Engineer |
HBA Architects |
Tel: 757-490-9048 |
| |
207 Business Park Drive, Suite 200 |
Fax: 757-490-7081 |
| |
Virginia Beach , VA 23462 |
|
| |
|
|
| Contractor |
RPC Industries |
Tel: 757-827-9625 |
| |
705 Industry Dr |
Fax: 757-827-5069 |
| |
Hampton, VA 23661 |
|
Back to Top
|
|

Building 100

Close-Up of Roof Prior to Construction

Completed Membrane Roof
|
 |