PMT Security Canopies

Project Description | Schedule | Project Team | Back to Archive

Archived: April 18, 2006

Project Description

The project consists of the construction of an overhead pre-engineered police canopy that will cover the inbound and outbound truck lanes at PMT, as well as an approximately 40 ft by 74 ft canopy which will cover a new 6 ft by 20 ft police security booth as well as both POV lanes in and out of the terminal. All the lanes will have security gates; however, the entrance will still be manned 24 hours a day, 7 days a week. The project also includes rerouting the existing 6 inch water main under Spencer Street to a new location around building 408 to Carolina Avenue. Conduit for possible future security upgrades (i.e. cameras, proximity card readers, etc.) will be placed as well.

Estimated Construction Cost: $1,558,060

Back to Top

Schedule

Phase
Target
Actual
Start Design January 2004 January 2004
Finish Design June 2004 June 30 , 2004
Advertise July 2004 July 25, 2004
Bids Due August 2004 August 24, 2004
Notice to Proceed September 15, 2005 October 11 , 2004
Final Completion January 31, 2006 March 13, 2006

Back to Top

Project Team

Project Manager Jousha M. Hill Tel: 757-628-8222
  Moffatt & Nichol Fax: 757-628-8244
     
Design Engineer Kimley Horn & Associates Tel: 757-548-7300
  501 Independence Pkwy, Ste 300 Fax: 757-548-7301
  Chesapeake, VA 23320  
     
Contractor R.D. Lambert & Son Tel: 757-420-5860
  1700 Lambert Court Fax: 757-420-1093
  Chesapeake, VA 23320  

Back to Top

 

 

 


Click to Enlarge Image
Site of POV and Main Gate Canopy Installations

Click to Enlarge Image
Completed Inspection Canopy

Click to Enlarge Image
Completed Main Gate Canopy

Click to Enlarge Image
Completed POV Canopy

 