Project Description
The project involves work necessary to demolish and remove Crane 4 and Crane 6 at the Portsmouth Marine Terminal. This work shall include crane demolition and removal of all material resulting from the demolition.
Estimated Construction Cost: $398,600
Back to Top
Schedule
Phase |
Target |
Actual |
| Start Design |
N/A |
N/A |
| Finish Design |
N/A |
N/A |
| Advertise |
January 23, 2005 |
January 23, 2005 |
| Bids Due |
February 8, 2005 |
February 8, 2005 |
| Notice to Proceed |
March 9, 2005 |
March 9, 2005 |
| Substantial Completion |
April 23, 2005 |
April 23, 2005 |
| Final Completion |
April 23, 2005 |
May 6, 2005 |
Back to Top
Project Team
| Project Manager |
Heath K. Pope, P.E. |
Tel: 757-628-8222 |
| |
Moffatt & Nichol |
Fax: 757-628-8244 |
| |
|
|
| Contractor |
East Coast Cranes |
Tel: 843-884-3929 |
| |
P.O. Box 328 |
Fax: 843-884-3929 |
| |
Isle of Palms, SC 29451 |
|
Back to Top
|
|

Crane 6 Demo

Continued Demo of Crane 6

All That's Left of Crane 6
|
 |