PMT Multi-Purpose Labor Support Facility

Project Description | Schedule | Project Team | Back to Archive

Archived: September 13, 2004

Project Description

The project involves the construction of a new 4600 square foot building, which includes masonry walls, wood trusses, plywood roof sheathing, metal standing seam roof, roof accessories, hollow metal doors and frames, door hardware glazing, plumbing, fire protection, heating air conditioning and ventilating, electrical systems, lighting and incidental related work. Interior finishes will include men's and women's restrooms and a kitchenette with cabinetry. Aside from the site work related to building construction, there will be concrete sidewalks connecting the three entrances of the building to the adjacent parking area.

Estimated Construction Cost: $731,215

Back to Top

Schedule

Phase
Target
Actual
Start Design Winter 2001/02 Winter 2001/02
Finish Design August 2002 August 2002
Advertise April 27, 2003 April 27, 2003
Bids Due May 29, 2003 May 29, 2003
Notice to Proceed June 30, 2003 July 1, 2003
Substantial Completion February 15, 2004 June 4, 2004
Final Completion March 15, 2004 August 23, 2004

Back to Top

Project Team

Project Manager Heath K. Pope, P.E. Tel: 757-628-8222
  Moffatt & Nichol Fax: 757-628-8244
     
Architect Transystems Tel: 757-627-1112
  Town Point Center Fax: 757-627-1113
  150 Boush St, Ste 1000  
  Norfolk, VA 23510  
     
Contractor Dow Construction, Inc. Tel: 757-558-6049
  4104 Holland Blvd #105 Fax: 757-558-6057
  Chesapeake, VA 23323  

Back to Top

 

 

 


Click to Enlarge Image
Completed Multi-Purpose Labor Support Facility

Click to Enlarge Image
Main Room

Click to Enlarge Image
Lavatory & Shower Facilities



 