PMT Storm Water Pond Maintenance

Project Description | Schedule | Project Team | Back to Archive

Archived: September 20, 2006

Project Description

Both the Storm Water Pond Basin No. 1 and CSX Pond Basin will undergo maintenance which will include clearing, grubbing, excavation of sediment material and installation of additional riprap.  Along with the pond maintenance, a 48” storm water outfall pipe will be installed adjacent to the existing outfall at Pond Basin No. 1.  These improvements will help improve both ponds' ability to treat storm water runoff at the terminal.

Estimated Construction Cost: $499,297

Back to Top

Schedule

Phase
Target
Actual
Start Design April 2005 April 2005
Finish Design June 2005 June 2005
Advertise November 30, 2006 November 30, 2006
Bids Due January 12, 2006 January 12, 2006
Notice to Proceed January 26, 2006 March 13, 2006
Substantial Completion March 27, 2006 August 3 , 2006
Final Completion April 26, 2006 September 4, 2006

Back to Top

Project Team

Project Manager Jousha M. Hill Tel: 757-628-8222
  Moffatt & Nichol Fax: 757-628-8244
     
Design Engineer Malcolm Pirnie Tel: 757- 873-8700
  701 Town Center Drive Fax: 757-873-8723
  Suite 600  
  Newport News, VA 23606  
     
Contractor Engineering & Environment, Inc. Tel: 757-457-0002
  195 S. Rosemont Road Fax: 757-457-3636
  Suite 118  
  Virginia Beach, VA 23452  

Back to Top

 

 

 


Click to Enlarge Image
Project Area

Click to Enlarge Image
Completed PMT Pond Basin No. 1

Click to Enlarge Image
Completed CSX Pond

Click to Enlarge Image
Completed Service Road

 