Project Description

The project consists of Installation of radiation detector portals at the main truck entrance at Portsmouth Marine Terminal. The portals will be temporarily installed on the two outbound lanes of the terminal. The stands will be mounted on temporary metal skids with a concrete counterweight in place of the permanent concrete foundations. The final installations will be made when the new Main Entrance Police Canopy is constructed. Similar radiation detectors have already been installed at Norfolk International Terminals and Newport News Marine Terminal.

Actual Construction Cost: $61,672

Back to Top

Schedule

Phase
Target
Actual
Start Design October 2003 October 2003
Finish Design October 2003 October 2003
Advertise N/A N/A
Bids Due N/A N/A
Notice to Proceed November 2003 November 2003
Substantial Completion December 26, 2003 January 15, 2004
Final Completion December 26, 2003 January 15, 2004

Back to Top

Project Team

Project Manger Heath K. Pope, P.E. Tel: 757-628-8222
  Moffatt & Nichol Fax: 757-628-8244
     
Contractor Challenge Constructors, Inc Tel: 757-393-2000
  450 Virginia Avenue Fax: 757-399-4191
  Portsmouth VA 23707  

Back to Top

 

 

 