PMT Reefer Relocation/Transfer Zone

Project Description | Schedule | Project Team | Back to Archive

Archived: July 2, 2007

Project Description

This project entails relocating the existing reefer storage row at PMT to the western side of the terminal and constructing a container transfer zone in its place. Work includes but is not limited to: site demolition, earthwork, underground utilities, electrical distribution system, asphalt, reinforced concrete pavement, traffic control and maintenance of traffic, sign and marking, E&S control, and all other miscellaneous items specified within the Construction Plans and Specifications.

Estimated Construction Cost: $5,053,675.00

Back to Top

Schedule

Phase
Target
Actual
Start Design August 2004 August 2004
Finish Design May 2005 May 2005
Advertise May 29, 2005 May 29, 2005
Bids Due June 28, 2005 July 6, 2005
Notice to Proceed September 1, 2005 September 1, 2005
Final Completion May 28, 2006 June 4 , 2007

Back to Top

Project Team

Project Manager Jousha M. Hill Tel: 757-628-8222
  Moffatt & Nichol Fax: 757-628-8244
     
Design Engineer Kimley Horn & Associates Tel: 757-548-7300
  501 Independence Pkwy, Ste 300 Fax: 757-548-7301
  Chesapeake, VA 23320  
     
Contractor S. B. Ballard Tel: 757-440-5555
  2828 Shipps Corner Road Fax: 757-451-2873
  Virginia Beach, VA 23453  

Back to Top

 

 

 


Click to Enlarge Image
Project Areas

Click to Enlarge Image
Completed Transfer Zone with Striping


Click to Enlarge Image
Checker Booth on East Side

Click to Enlarge Image
Completed Reefer Row

 