PMT Reefer Relocation/Transfer Zone
Project Description | Schedule | Project Team | Back to Archive
Archived: July 2, 2007
Project Description
This project entails relocating the existing reefer storage row at PMT to the western side of the terminal and constructing a container transfer zone in its place. Work includes but is not limited to: site demolition, earthwork, underground utilities, electrical distribution system, asphalt, reinforced concrete pavement, traffic control and maintenance of traffic, sign and marking, E&S control, and all other miscellaneous items specified within the Construction Plans and Specifications.
Estimated Construction Cost: $5,053,675.00
Back to Top
Schedule
Phase |
Target |
Actual |
| Start Design |
August 2004 |
August 2004 |
| Finish Design |
May 2005 |
May 2005 |
| Advertise |
May 29, 2005 |
May 29, 2005 |
| Bids Due |
June 28, 2005 |
July 6, 2005 |
| Notice to Proceed |
September 1, 2005 |
September 1, 2005 |
| Final Completion |
May 28, 2006 |
June 4 , 2007 |
Back to Top
Project Team
| Project Manager |
Jousha M. Hill |
Tel: 757-628-8222 |
| |
Moffatt & Nichol |
Fax: 757-628-8244 |
| |
|
|
| Design Engineer |
Kimley Horn & Associates |
Tel: 757-548-7300 |
| |
501 Independence Pkwy, Ste 300 |
Fax: 757-548-7301 |
| |
Chesapeake, VA 23320 |
|
| |
|
|
| Contractor |
S. B. Ballard |
Tel: 757-440-5555 |
| |
2828 Shipps Corner Road |
Fax: 757-451-2873 |
| |
Virginia Beach, VA 23453 |
|
Back to Top
|
|

Project Areas

Completed Transfer Zone with Striping

Checker Booth on East Side

Completed Reefer Row
|
 |