PMT Seaboard Avenue Vortechnics Unit

Project Description | Schedule | Project Team | Back to Archive

Archived: October 21, 2005

Project Description

This project consists of providing and installing a pre-fabricated Vortechnics stormwater treatment system at Portsmouth Marine Terminal. The project includes but is not limited to erosion and sediment control, site demolition, earthwork, underground utilities, and other miscellaneous items.

Estimated Construction Cost: $180,700

Back to Top

Schedule

Phase
Target
Actual
Start Design N/A N/A
Finish Design February 13, 2005 February 20, 2005
Advertise February 20, 2005 February 20, 2005
Bids Due March 24, 2005 March 24, 2005
Notice to Proceed April 15, 2005 April 15, 2005
Substantial Completion June 14, 2005 October 11, 2005
Final Completion July 14, 2005 October 11, 2005

Back to Top

Project Team

Project Manager Jousha M. Hill Tel: 757-628-8222
  Moffatt & Nichol Fax: 757-628-8244
     
Contractor Homeland Contracting Corporation Tel: 757-631-6710
  738 Sheraton Court Fax: 757-631-6711
  Virginia Beach, VA 23452  

Back to Top

 

 

 

Click to Enlarge Image
Completed Project Area

Click to Enlarge Image
Installed Unit 9/23/05

Click to Enlarge Image
Bypass Structures