PMT Seaboard Avenue Vortechnics Unit
Project Description | Schedule | Project Team | Back to Archive
Archived: October 21, 2005
Project Description
This project consists of providing and installing a pre-fabricated Vortechnics stormwater treatment system at Portsmouth Marine Terminal.
The project includes but is not limited to erosion and sediment control, site demolition, earthwork, underground utilities, and other miscellaneous items.
Estimated Construction Cost: $180,700
Back to Top
Schedule
Phase |
Target |
Actual |
| Start Design |
N/A |
N/A |
| Finish Design |
February 13, 2005 |
February 20, 2005 |
| Advertise |
February 20, 2005 |
February 20, 2005 |
| Bids Due |
March 24, 2005 |
March 24, 2005 |
| Notice to Proceed |
April 15, 2005 |
April 15, 2005 |
| Substantial Completion |
June 14, 2005 |
October 11, 2005 |
| Final Completion |
July 14, 2005 |
October 11, 2005 |
Back to Top
Project Team
| Project Manager |
Jousha M. Hill |
Tel: 757-628-8222 |
| |
Moffatt & Nichol |
Fax: 757-628-8244 |
| |
|
|
| Contractor |
Homeland Contracting Corporation |
Tel: 757-631-6710 |
| |
738 Sheraton Court |
Fax: 757-631-6711 |
| |
Virginia Beach, VA 23452 |
|
Back to Top
|
|

Completed Project Area

Installed Unit 9/23/05

Bypass Structures
|
 |