Project Description

The construction at this site is to consist of demolition of existing concrete pavement and construction of new reinforced concrete pavement adjacent to the Clyde Rail. The construction area will encompass several sets of rails, including the wharf crane rail, the Clyde crane rail, and the standard rail running on the wharf.

Estimated Construction Cost: $132,700

Back to Top

Schedule

Phase
Target
Actual
Start Design October 2002 October 2002
Finish Design September 2003 September 2003
Advertise November 2, 2003 November 2, 2003
Bids Due December 14, 2003 December 14, 2003
Notice to Proceed January 2004 February 2, 2004
Substantial Completion February 28, 2004 March 10, 2004
Final Completion March 5, 2004 March 31, 2004

Back to Top

Project Team

Project Manager Heath K. Pope, P.E. Tel: 757-628-8222
  Moffatt & Nichol Fax: 757-628-8244
     
Contractor Century Concrete, Inc. Tel: 757-460-5366
  1364 Air Rail Avenue Fax: 757- 460-3296
  Virginia Beach , VA 23455  

Back to Top

 

 


Click to Enlarge Image
Completed Repairs

Click to Enlarge Image
Detail Work Around Rail

Click to Enlarge Image
Damaged Pavement Prior to Repairs

 

About This Site
Moffatt & Nichol Web Site