PMT Wharf Pavement Repairs
Project Description | Schedule | Project Team | Back to Archive
Archived: June 10, 2004
Project Description
The construction at this site is to consist of demolition of existing concrete pavement and construction of new reinforced concrete pavement adjacent to the Clyde Rail. The construction area will encompass several sets of rails, including the wharf crane rail, the Clyde crane rail, and the standard rail running on the wharf.
Estimated Construction Cost: $132,700
Back to Top
Schedule
Phase |
Target |
Actual |
| Start Design |
October 2002 |
October 2002 |
| Finish Design |
September 2003 |
September 2003 |
| Advertise |
November 2, 2003 |
November 2, 2003 |
| Bids Due |
December 14, 2003 |
December 14, 2003 |
| Notice to Proceed |
January 2004 |
February 2, 2004 |
| Substantial Completion |
February 28, 2004 |
March 10, 2004 |
| Final Completion |
March 5, 2004 |
March 31, 2004 |
Back to Top
Project Team
| Project Manager |
Heath K. Pope, P.E. |
Tel: 757-628-8222 |
| |
Moffatt & Nichol |
Fax: 757-628-8244 |
| |
|
|
| Contractor |
Century Concrete, Inc. |
Tel: 757-460-5366 |
| |
1364 Air Rail Avenue |
Fax: 757- 460-3296 |
| |
Virginia Beach , VA 23455 |
|
Back to Top |
|

Completed Repairs

Detail Work Around Rail

Damaged Pavement Prior to Repairs
|