Project Description

The project includes the construction of approximately 3,000 linear feet of heavy duty shuttle carrier pavement along Bulkhead Avenue from Third Street to Lagoon Avenue. Construction activities include erosion and sediment control, site demolition, earthwork, drainage, water distribution, asphalt pavement, concrete pavement, waterfront structural improvements, rail crossings, site lighting, electrical ductbank, utilities, traffic control, construction phasing, and tie-in with existing waterfront features, drainage lines and rail yard facilities.  The work will include all other miscellaneous items specified with the Construction Plans and Specifications.

When complete, the new shuttle carrier road will allow for the efficient movement of containers between NIT North and NIT South via shuttle carrier vehicle.

Estimated Construction Cost: $8,210,500

Back to Top

Schedule

Phase
Target
Actual
Start Design October 15, 2006 October 15, 2006
Finish Design June 1 , 2007 June 1, 2007
Advertise June 3, 2007 June 3, 2007
Bids Due July 19, 2007 July 19, 2007
Notice to Proceed August 31, 2007 September 1, 2007
Substantial Completion July 1, 2008 December 2008
Final Completion July 31, 2008 February 15, 2009

Back to Top

Project Team

Project Manager Andy Kondysar, P.E. Tel: 757-683-9902
  Virginia Port Authority Fax: 757-683-2151
     
Design Engineer MMM Design Group Tel: 757-623-1641
  300 Main Street
Fax: 757-623-5809
  Suite 200  
  Norfolk, VA 23510  
     
Contractor E.V. Williams, Inc. Tel: 757-420-1140
  925 S. Military Highway Fax: 757-420-7250
  Virginia Beach, VA 23464  

Back to Top

 

 

 


Click to Enlarge Image
Project Area

Click to Enlarge Image
Close-up of Route

Click to Enlarge Image
Completed Shuttle Carrier Road in Use

Click to Enlarge Image
Shuttle Carrier Vehicle

 

About This Site
Moffatt & Nichol Web Site