Project Description

This project consists of the renovation of the interior lobby of the NIT Control Tower. The work includes new ceilings, wall finishes, painting, casework, signage, and incidental related work. 

Estimated Construction Cost: $25,000

Back to Top

Schedule

Phase
Target
Actual
Bids Due February 4, 2004 February 4, 2004
Notice to Proceed March 23, 2004 March 23, 2004
Substantial Completion April 5, 2004 April 13, 2004
Final Completion April 12, 2004 July 9, 2004

Back to Top

Project Team

Project Manager Barbara Bodenstein, E.I.T. Tel: 757-628-8222
  Moffatt & Nichol Fax: 757-628-8244
     
Contractor Spacemakers Tel: 757-640-8100
  768 West 20th Street Fax: 757-640-8600
  P.O. Box 11104  
  Norfolk, VA 23517  