VIP Administration Building Addition

Project Description | Schedule | Project Team | Back to Archive

Archived: December 22, 2006

Project Description

The project involves the work necessary to construct a two-story, approximately 1200 square-foot addition to the existing administration building at the Virginia Inland Port. The addition will provide space for a new lobby with an entrance vestibule, a new storage room, a mechanical room and a new computer room.

Estimated Construction Cost: $588,836

Back to Top

Schedule

Phase
Target
Actual
Start Design January 1, 2004 January 1, 2004
Finish Design June 11, 2004 June 11, 2004
Advertise June 13, 2004 February 20, 2005
Bids Due July 13, 2004 March 29, 2005
Notice to Proceed April 30, 2005 June 27, 2005
Final Completion November 30, 2005 December 8, 2006

Back to Top

Project Team

Project Manager Jousha M. Hill Tel: 757-628-8222
  Moffatt & Nichol Fax: 757-628-8244
     
Architect HBA Architects Tel: 757-490-9048
  One Columbus Center #1000 Fax: 757-490-7081
  Virginia Beach , VA 23462  