Project Description
The project consists of the construction of approximately 7.5 acres of new container storage, which will include soil and rock excavation, fill operations to raise existing grades, asphalt paving, extending existing stormwater drain inlets to new grade elevations, installation of additional yard lighting to cover the expanded yard, and some tree planting at the terminal entrance. Also as part of this project, repairs will be made to the existing stormwater pond, installing a clay liner in the pond, as well as performing additional repairs to several areas throughout the inland port that have experienced erosion damage.
Estimated Construction Cost: $1,760,000
Back to Top
Schedule
Phase |
Target |
Actual |
| Start Design |
November 2002 |
November 2002 |
| Finish Design |
August 2003 |
August 2003 |
| Advertise |
August 2003 |
August 2003 |
| Bids Due |
September 8, 2003 |
September 8, 2003 |
| Notice to Proceed |
September 15, 2003 |
October 2, 2003 |
| Substantial Completion |
November 27, 2003 |
May 7, 2004 |
| Final Completion |
December 27, 2003 |
June 28, 2004 |
Back to Top
Project Team
| Project Manager |
Heath K. Pope, P.E. |
Tel: 757-628-8222 |
| |
Moffatt & Nichol |
Fax: 757-628-8244 |
| |
|
|
| Design Engineer |
Kimley Horn & Associates |
Tel: 757-548-7300 |
| |
501 Independence Pkwy |
Fax: 757-548-7301 |
| |
Suite 300 |
|
| |
Chesapeake, VA 23320 |
|
| |
|
|
| Contractor |
Ricketts Construction Co. |
Tel: 540-662-4164 |
| |
36 Ricketts Dr |
Fax: 540-722-6080 |
| |
Winchester, VA 22601 |
|