VIP Pavement Expansion

Project Description | Schedule | Project Team | Back to Archive

Archived: July 1, 2004

Project Description

The project consists of the construction of approximately 7.5 acres of new container storage, which will include soil and rock excavation, fill operations to raise existing grades, asphalt paving, extending existing stormwater drain inlets to new grade elevations, installation of additional yard lighting to cover the expanded yard, and some tree planting at the terminal entrance. Also as part of this project, repairs will be made to the existing stormwater pond, installing a clay liner in the pond, as well as performing additional repairs to several areas throughout the inland port that have experienced erosion damage.

Estimated Construction Cost: $1,760,000

Back to Top

Schedule

Phase
Target
Actual
Start Design November 2002 November 2002
Finish Design August 2003 August 2003
Advertise August 2003 August 2003
Bids Due September 8, 2003 September 8, 2003
Notice to Proceed September 15, 2003 October 2, 2003
Substantial Completion November 27, 2003 May 7, 2004
Final Completion December 27, 2003 June 28, 2004

Back to Top

Project Team

Project Manager Heath K. Pope, P.E. Tel: 757-628-8222
  Moffatt & Nichol Fax: 757-628-8244
     
Design Engineer Kimley Horn & Associates Tel: 757-548-7300
  501 Independence Pkwy Fax: 757-548-7301
  Suite 300  
  Chesapeake, VA 23320  
     
Contractor Ricketts Construction Co. Tel: 540-662-4164
  36 Ricketts Dr Fax: 540-722-6080
  Winchester, VA 22601  

Back to Top

 

 

 


Click to Enlarge Image
Aerial View of Expansion Area

Click to Enlarge Image
Completed Asphalt Paving & Striping

Click to Enlarge Image
Curb and Gutter

 

 