NIT Warehouse 1, 2 & 3 Area Improvements

Project Description | Schedule | Project Team | Back to Archive

Archived: December 2, 2003

Project Description

This project consists of the movement of approximately 175,000 cubic yards of soil formerly used as surcharge at the northern end of NIT on the site of what will be the new VPA Command and Control Center. The soil is to be moved to the area where Warehouses 1, 2 & 3 used to stand and compacted to serve as a suitable base for new pavement.

Actual Construction Cost: $750,000

Back to Top

Schedule

Phase
Target
Actual
Start Design December 2002 December 2002
Finish Design March 2003 March 2003
Advertise April 2003 April 2003
Bids Due June 2003 June 2003
Notice to Proceed July 2003 July 2003
Substantial Completion September 2003 November 2003
Final Completion October 2003 November 2003

Back to Top

Project Team

Project Manager Kevin P. Abt, P.E. Tel: 757-683-2139
  Virginia Port Authority Fax: 757-683-2151
     
Contractor Higgerson Buchanan, Inc. Tel: 757-545-4665
  P.O. Box 1128 Fax: 757-543-8930
  5300 Bainbridge Blvd.  
  Chesapeake, VA 23320  

Back to Top

 

 

 


Click to Enlarge Image
Site Grading After Demo

Click to Enlarge Image
Site Grading After Demo