NIT Warehouse 1, 2 & 3 Area Improvements
Project Description | Schedule | Project Team | Back to Archive
Archived: December 2, 2003
Project Description
This project consists of the movement of approximately 175,000 cubic yards of soil formerly used as surcharge at the northern end of NIT on the site of what will be the new VPA Command and Control Center. The soil is to be moved to the area where Warehouses 1, 2 & 3 used to stand and compacted to serve as a suitable base for new pavement.
Actual Construction Cost: $750,000
Back to Top
Schedule
Phase |
Target |
Actual |
| Start Design |
December 2002 |
December 2002 |
| Finish Design |
March 2003 |
March 2003 |
| Advertise |
April 2003 |
April 2003 |
| Bids Due |
June 2003 |
June 2003 |
| Notice to Proceed |
July 2003 |
July 2003 |
| Substantial Completion |
September 2003 |
November 2003 |
| Final Completion |
October 2003 |
November 2003 |
Back to Top
Project Team
| Project Manager |
Kevin P. Abt, P.E. |
Tel: 757-683-2139 |
| |
Virginia Port Authority |
Fax: 757-683-2151 |
| |
|
|
| Contractor |
Higgerson Buchanan, Inc. |
Tel: 757-545-4665 |
| |
P.O. Box 1128 |
Fax: 757-543-8930 |
| |
5300 Bainbridge Blvd. |
|
| |
Chesapeake, VA 23320 |
|