Project Description

The project is the demolition and removal of seven (7) cells of each of the warehouse buildings listed above and select underground utilities, the installation/relocation of various utilities including communications, water, storm drainage and electric, installation of asphalt pavement, coordination of work and assorted minor tasks.

Estimated Construction Cost: $2,300,000

Back to Top

Schedule

Phase
Target
Actual
Start Design April 2003 April 2003
Finish Design July 2003 July 2003
Advertise July 2003 July 2003
Bids Due August 2003 August 2003
Notice to Proceed September 2003 September 2003
Substantial Completion December 2003 March 2004
Final Completion January 2004 June 2004

Back to Top

Project Team

Project Manager Kevin P. Abt, P.E. Tel: 757-683-2139
  Virginia Port Authority Fax: 757-683-2151
     
Contractor WACO, Inc. Tel: 757-558-3100
  1326 Cavalier Boulevard Fax: 757-558-3106
  Chesapeake, VA 23323  

Back to Top

 

 

 

Click to Enlarge Image
Completed Demolition

Click to Enlarge Image
Partial Demolition

Click to Enlarge Image
Project Site Prior to Demolition

About This Site
Moffatt & Nichol Web Site