NIT Warehouses 4 & 5 Demolition
Project Description | Schedule | Project Team | Back to Archive
Archived: June 29, 2004
Project Description
The project is the demolition and removal of seven (7) cells of each of the warehouse buildings listed above and select underground utilities, the installation/relocation of various utilities including communications, water, storm drainage and electric, installation of asphalt pavement, coordination of work and assorted minor tasks.
Estimated Construction Cost: $2,300,000
Back to Top
Schedule
Phase |
Target |
Actual |
| Start Design |
April 2003 |
April 2003 |
| Finish Design |
July 2003 |
July 2003 |
| Advertise |
July 2003 |
July 2003 |
| Bids Due |
August 2003 |
August 2003 |
| Notice to Proceed |
September 2003 |
September 2003 |
| Substantial Completion |
December 2003 |
March 2004 |
| Final Completion |
January 2004 |
June 2004 |
Back to Top
Project Team
| Project Manager |
Kevin P. Abt, P.E. |
Tel: 757-683-2139 |
| |
Virginia Port Authority |
Fax: 757-683-2151 |
| |
|
|
| Contractor |
WACO, Inc. |
Tel: 757-558-3100 |
| |
1326 Cavalier Boulevard |
Fax: 757-558-3106 |
| |
Chesapeake, VA 23323 |
|
Back to Top
|
|

Completed Demolition

Partial Demolition

Project Site Prior to Demolition
|
 |