| |
NIT South Renovations - Backlands Reconstruction
Project Description | Current Status | Schedule | Related Documents
Photo Galleries | Project Team
Last Updated: July 28, 2008
Project Description
This project entails the complete renovation of the south container yard of Norfolk International Terminals. The entire project area comprises approximately 150 acres and is being completed in stages so as not to interfere with cargo operations. Work includes
utility upgrades and pavement improvements.
Original Estimated Construction Cost (Areas 3 and 4): $27,535,000
Change Order for Work in Areas 5 Through 7: $14,900,000
Change Order for Work in Areas 10A Through 12B: $4,900,000
Back to Top
Current Status
The movement of surcharge materials from Area 6/7 to Area 8 is complete. RCC placement in Area 6/7 in underway, and asphalt placement should begin in four to five weeks. Overall, construction of Area 6/7 is approximately 50% complete. The change order for the construction of Area 8 is under consideration.
Back to Top
Schedule
Phase |
Target |
Actual |
| Start Design |
January 2005 |
January 2005 |
| Finish Design |
August 2005 |
August 2005 |
| RFQ Issued |
July 2005 |
July 17, 2005 |
| RFQ Responses Due |
August 2005 |
August 5, 2005 |
| Bids Due |
September 2005 |
September 20, 2005 |
| Notice to Proceed |
October 2005 |
November 14, 2005 |
Substantial Completion Area 3 |
September 2006 |
June 2, 2006 |
| Substantial Completion Area 4 |
November 2007 |
December 2006 |
| Substantial Completion Area 5/6 |
November 2007 |
September 2007 |
| Substantial Completion Area 6/7 |
November 2008 |
Estimated October 2008 |
| Substantial Completion Area 8 |
July 2009 |
Estimated July 2009 |
| Final Completion |
December 2012 |
Estimated December 2011 |
Back to Top
Related Documents
These documents will open in a new window. You may need Adobe® Reader to view some of these documents. Click here to download a free version.
| There are no related documents currently posted for this project. |
Back to Top
Photo Galleries
Back to Top
|
|

NIT South Backlands Project Areas

Backlands Progress as of July 2008

NIT South July 2008

Close Up of Areas 6/7 & 8

Construction in Area 6/7
|
 |