NIT South Renovations - Backlands Reconstruction
Project Description | Current Status | Schedule | Related Documents
Photo Galleries | Project Team
Last Updated: April 14, 2010
Project Description
This project entails the complete renovation of the south container yard of Norfolk International Terminals. The entire project area comprises approximately 150 acres and is being completed in stages so as not to interfere with cargo operations. Work includes
utility upgrades and pavement improvements.
Original Estimated Construction Cost (Areas 3 and 4): $27,535,000
Change Order for Work in Areas 5 Through 7: $14,900,000
Change Order for Work in Area 8: $10,000,000
Change Order for Work in Areas 10A Through 12B: $4,900,000
Change Order for Work in Area 9: $6,900,000
Back to Top
Current Status
Work in Area 9 is underway, trench drain construction is complete and stormwater pipe is being laid. Paving operations will begin in early May.
Back to Top
Schedule
Phase |
Target |
Actual |
| Start Design |
January 2005 |
January 2005 |
| Finish Design |
August 2005 |
August 2005 |
| RFQ Issued |
July 2005 |
July 17, 2005 |
| RFQ Responses Due |
August 2005 |
August 5, 2005 |
| Bids Due |
September 2005 |
September 20, 2005 |
| Notice to Proceed |
October 2005 |
November 14, 2005 |
Substantial Completion Area 3 |
September 2006 |
June 2, 2006 |
| Substantial Completion Area 4 |
November 2007 |
December 2006 |
| Substantial Completion Area 5/6 |
November 2007 |
September 2007 |
| Substantial Completion Area 6/7 |
November 2008 |
November 2008 |
| Substantial Completion Area 8 |
July 2009 |
October 31, 2009 |
| Final Completion |
December 2012 |
Estimated August 2010 |
Back to Top
Related Documents
These documents will open in a new window. You may need Adobe® Reader to view some of these documents. Click here to download a free version.
| There are no related documents currently posted for this project. |
Back to Top
Photo Galleries
Back to Top |
|

NIT South October 2009

Earth Moving in Area 9

Area 9
|