ProjectsResourcesCapital Outlay Manual Coming SoonVPA Engineering Home
 


NIT South Renovations - Backlands Reconstruction

Project Description | Current Status | Schedule | Related Documents
Photo Galleries | Project Team

Last Updated: July 28, 2008

Project Description

This project entails the complete renovation of the south container yard of Norfolk International Terminals. The entire project area comprises approximately 150 acres and is being completed in stages so as not to interfere with cargo operations. Work includes utility upgrades and pavement improvements.

Original Estimated Construction Cost (Areas 3 and 4): $27,535,000
Change Order for Work in Areas 5 Through 7: $14,900,000
Change Order for Work in Areas 10A Through 12B: $4,900,000

Back to Top

Current Status

The movement of surcharge materials from Area 6/7 to Area 8 is complete. RCC placement in Area 6/7 in underway, and asphalt placement should begin in four to five weeks. Overall, construction of Area 6/7 is approximately 50% complete. The change order for the construction of Area 8 is under consideration.

Back to Top

Schedule

Phase
Target
Actual
Start Design January 2005 January 2005
Finish Design August 2005 August 2005
RFQ Issued July 2005 July 17, 2005
RFQ Responses Due August 2005 August 5, 2005
Bids Due September 2005 September 20, 2005
Notice to Proceed October 2005 November 14, 2005

Substantial Completion Area 3

September 2006 June 2, 2006
Substantial Completion Area 4 November 2007 December 2006
Substantial Completion Area 5/6 November 2007 September 2007
Substantial Completion Area 6/7 November 2008 Estimated October 2008
Substantial Completion Area 8 July 2009 Estimated July 2009
Final Completion December 2012 Estimated December 2011

Back to Top

Related Documents

These documents will open in a new window. You may need Adobe® Reader to view some of these documents. Click here to download a free version.

There are no related documents currently posted for this project.

Back to Top

Photo Galleries

Continued Work in Areas 6/7 & 8 3/13/08
Work on Area 8 Begins 1/16/08
Area 10 Joint Repair 11/9/07
Progress Photos 10/16/07
Continued Work on Areas 5, 6 & 7 7/11/07
RCC Placement in Area 5/6 6/5/07
Wick Drain Installation in Area 6/7 3/12/07
Area 5/6 Surcharge Removal 2/27/07
Demo in Area 6/7 1/9/07
AC Area 4, Surcharge Area 5 11/28/06
Progress Photos 10/30/06
Area 4 Transfer Zone, Surcharge in Area 5 9/7/06
Progress Photos 7/11/06
Progress Photos - Area 3 5/30/06

Back to Top

 

 

 


Click to Enlarge Image
NIT South Backlands Project Areas

Click to Enlarge Image
Backlands Progress as of July 2008

Click to Enlarge Image
NIT South July 2008

Click to Enlarge Image
Close Up of Areas 6/7 & 8

Click to Enlarge Image
Construction in Area 6/7

 

 

About This Site
Moffatt & Nichol Web Site