NIT Central Rail Project
Project Description | Current Status | Schedule | Related Documents
Photo Galleries | Project Team
Last Updated: September 3, 2008
Project Description
The project calls for the installation of approximately 11,000 feet of track, ties and ballast, several switches, heavy-duty pavement in the rail yard area, site civil utility work and electrical work. When complete, this project will provide a centralized rail yard for NIT and significantly increase rail capacity at the terminal.
Current Estimated Construction Cost:
$16,476,450
Back to Top
Current Status
Earthwork operations are continuing on the eastern side of the project site. Utility work is nearing completion. Work on the last road and rail area adjacent to Fifth Street has begun. RCC pavement operations are complete, concrete pavement placement is 90% complete, and the crossing of Railroad Avenue with the new rail spurs has begun. Overall project is 80% complete.
Back to Top
Schedule
Phase |
Target |
Actual |
| Start Design |
June 29, 2006 |
June 29, 2006 |
| Finish Design |
February 2007 |
March 2007 |
| Advertise |
April 2007 |
April 1, 2007 |
| Bids Due |
May 8, 2007 |
May 8, 2007 |
| Notice to Proceed |
August 1, 2007 |
August 1, 2007 |
| Substantial Completion |
July 2, 2008 |
Estimated September 2008 |
| Final Completion |
August 1, 2008 |
Estimated October 2008 |
Back to Top
Related Documents
These documents will open in a new window. You may need Adobe® Reader to view some of these documents. Click here to download a free version.
| There are no related documents currently posted for this project. |
Back to Top
Photo Galleries
Back to Top
|
|

Project Location

Project Progress as of July 2008

Earthwork Operations

New Switches to Central Rail Yard
|
 |