NIT Central Rail Project Phase II

Project Description | Current Status | Schedule | Project Team

Last Updated: March 7, 2012

Project Description

This project is a follow-on to Phase I of the Central Rail Project to double the capacity of the existing rail yard at Norfolk International Terminal.  The project includes demolition of an old warehouse and removal of the utilities to make way for the new rail yard, followed by the installation of six new rail lines for loading containerized cargo.  The rail work expansion will add approximately 13,000 linear feet of railroad track and have heavy duty concrete pavement for port vehicles transporting containers from the ship cranes to the rail yard.. The project also includes upgrades to the water, drainage, sanitary, electrical and communication systems.

The project is funded through ARRA in conformance with the requirements of FHWA and VDOT.

Estimated Construction Cost: $10,100,000

Back to Top

Current Status

The rail yard project was completed on July 22, 2011 and the tracks are now being used by VIT.

Back to Top

Schedule

Phase
Target
Actual
Start Design June 29, 2006 June 29, 2006
Finish Design February 2007 March 2007
Advertise (Phase II) October 2009 October 2009
Bids Due January 2010 January 2010
Notice to Proceed February 22, 2010 February 22, 2010
Substantial Completion March 2011 June 22, 2011
Final Completion April 2011 July 22, 2011

Back to Top

 

 

 



Aerial of Completed Central Rail Yard


Completed Central Rail Yard

Bypass Track in Front of Vehicle Maintenance


Rail Yard in Use