NIT Main Gate Rail Yard Rebuild
Project Description | Current Status | Schedule | Project Team
Last Updated: May 18, 2012
Project Description
The purpose of this project is to rebuild track 4 and complete critical repairs to tracks 2 and 3 at the NIT Main Gate rail yard. The lap switch at Hampton Blvd. will be replaced as will the switch that leads to tracks four and five. Track four, from the second switch to the crossover to track five near vehicle maintenance will be rebuilt with new ties and rail. Tracks two and three will have new ties placed at all track joints, and every fifth tie will also be replaced. In addition, any “Dutchmen” in tracks two and three will be replaced. All splice bars and switches will be checked to insure the bolts are tight.
Current Estimated Construction Cost: $1,018,000
Back to Top
Current Status
Construction is underway. The main gate yard repair/upgrade is complete except for the final ballast regulation. The contractor will activate new runaround track next week and proceed with remaining demo and yard track construction.
Back to Top
Schedule
Phase |
Target |
Actual |
| Notice to Proceed |
June 30, 2011 |
June 30, 2011 |
| Final Completion |
January 1, 2012 |
Anticipated May 2012 |
Back to Top
|
|

Track 2,3 and 4 repairs

Repair of tracks 2, 3 and 4 south

Repair of tracks 2, 3 and 4 south
|
 |