NIT North Wharf Extension
Project Description | Current Status | Schedule | Related Documents
Photo Galleries | Project Team
Last Updated: September 3, 2008
Project Description
The project generally includes, but is not limited to: extension of the existing wharf approximately 900 feet north, dredging of the adjacent access channel and berth area, site civil work behind the wharf structure, and associated utility work. The project also includes the procurement of three container cranes similar to those at the south end of the NIT North Wharf.
Current Estimated Construction Cost: $34,000,000
Back to Top
Current Status
The project is complete.
Back to Top
Schedule
Phase |
Target |
Actual |
| Start Design |
March 1, 2006 |
March 1, 2006 |
| Finish Design |
August 7, 2006 |
September 8, 2006 |
| Advertise |
August 30, 2006 |
September 17, 2006 |
| Bids Due |
September 30, 2006 |
October 17, 2006 |
| Notice to Proceed |
October 16, 2006 |
January 3, 2007 |
| Substantial Completion |
May 31, 2008 |
June 30, 2008 |
| Final Completion |
June 30, 2008 |
July 30, 2008 |
Back to Top
Related Documents
These documents will open in a new window. You may need Adobe® Reader to view some of these documents. Click here to download a free version.
Back to Top
Photo Galleries
Back to Top
|
|

Location of NIT North Wharf Extension

Wharf Extension Prior to Arrival of Cranes

New Wharf & Backlands After Crane Arrival

New Wharf & Backlands After Crane Arrival
|
 |