![]() |
||||
Project Status & Schedule Heartland Corridor Clearance Project Web Site
|
Project Status and Schedule Last Updated: April 14, 2010 The Operating Agreement with Commonwealth Railway is currently being finalized. It will likely be a few weeks to a month until the Agreement is finalized and service on the new line begins. The rail line has been connected at each end and is now complete. Operation of the rail within the median will proceed after completion of the Operating Agreement. Traffic has been routed to the new Route 17 Bridge. Asphalt pavement work for the remaining lanes and the ramp from I-664 will be complete this month. Demolition of the detour road and completion of the remaining drainage and utility items is underway. After the final layer of asphalt and pavement markings are complete, all lanes on the bridge will be in use and the ramp from I-664 will be reopened.
|
|||
|
|
![]() |
|||